Crusher move, Ft Mac

polarice

Active VIP Member
Joined
Jan 8, 2008
Messages
14,849
Reaction score
2,206
Location
Calgary, Alberta, Canada
Planning, planning and more planning..lol. There was also plant production to consider so it is all tied into numerous other things. You are correct about the road, t was built for this move and continued to the new location. All of the conveyor sections were also moved as well and placed on new structure that was pre assembled. What takes time is planning out all the steps of this kind of job, all on plant outages as the thing needs to produce as soon as possible.

These kind of projects usually take several years of pre work, all leading up to the big event. In this case, a 40 day shutdown to get it all done start to finish.

Cheers ! :beer:

theres a whole bunch involved that the people dont think about
 
Top Bottom