If existing pad is really good it can be done. But to make it the best epoxy rebar every 16" (should be drilled in every place), only need to drill in 4"-6" or so. With epoxy in, it will tear the concrete apart before that rebar will ever pull out. Do it all the time on bigger slabs with multiple pours instead of sticking rebar out.
But OP pad is 30 years old, way to old to be adding onto. Infact almost guaranteed if you tried to drill in you would see how soft the concrete has gotten. Plus that concrete is probably like 20 MPA if your REALLY lucky.
THIS IS THE DUMBEST post i have ever read. concrete continues to gain strength for up to 75 years. if your lucky you would be able to drill into it.soft.......OOK.
that concrete is stronger than it was 28 days after it was poured 30 years ago.